Project Milestones

Project Milestones

Project
Milestone
Description
(Days from
Appointed
Date )
Planned Achieved actual Current
Physical Status
Physical
Status (%)
Schedule
Date
Physical
Progress
Achieved Date
Project Milestone-I15020%07-07-2022
Project Milestone-II33035%03-01-2023
Project Milestone-III51075%02-07-2023
Schedule Completion Date730100%07-02-2024