Project Name | Construction of Eight lane access-controlled Expressway from Km 26.582 to Km 50.700 of Main Expressway and Km 0+0 to Km 3+000 of SPUR (Shirsad to Masvan Section of Vadodara Mumbai Expressway) in the State of Maharashtra on Hybrid Annuity mode under BharatmalaPariyojana (Phase II-Package XIII) |
Scheme/Phase | BharatmalaPariyojna/ Phase II |
---|
Mode of Execution | HAM |
---|
No. of Lanes/Configuration | Eight Lane/ Rigid Pavement |
---|
Bid Project Cost | 2747 Cr. |
---|
No. Of Minor Bridges | 05 Nos. |
---|
No. of Culverts (Box/Slab/Pipe) | 67 Nos. |
---|
No. of Major Bridges | 06 Nos. |
---|
No. of Underpasses (SVUP/LVUP/VUP) | 30 Nos. |
---|
No. of Interchanges | 02 Nos. |
---|
Toll Plaza | 08 Nos. |
---|
Rest Area | 02 Nos. |
---|
Concessionaire Name | G R SHIRSAD MASVAN EXPRESSWAY PRIVATE LIMITED |
---|
Date of Letter of Award(LOA) | 15.10.2020 |
---|
Appointed Date | 08.02.2022 |
---|
Construction Period (in Days) | 730 Days |
---|
Schedule Completion Date | 730 days from Appointed Date |
---|
Operation & Maintenance Period | 15 Years from the Commercial Operation Date |
---|
Independent Engineer | M/sL N Malviya Infra Projects Ltd. in JV with M/s Highway Consultant Pvt. Ltd. |
---|
Authority Name | National Highways Authority of India |
---|
Independent Engineer Mobilization Date | 09.08.2021 |
---|